BRIDGES |
| ||
ROAD BRIDGE OVER THE DANUBE AT BOGOJEVO – CROATIA | ROAD BRIDGE OVER THE BOLJETINSKA RIVER | |
The bridge consists of two independent steel structures:
The structure erection is performed by a floating crane. The cantilever procedure on principle of cantilever erection is applied to the great span, and temporary supports are used for other spans. Two piers on navigation route are founded to caissons, and the others to HW piles with 120 mm diameter The overall length of the bridge is 670 m. | At a height of 54 m above the river bed, Boljetinska river canyon is spanned by two reinforced concrete arches with a span of The road surface is a continuous beam over seven plains with a span of 16 m each. The arch abutments and piers on the river banks are founded to a limestone rock. The falsework erection and transportation of equipment as well as material are performed by a cable crane with a carrying capacity of 6 t. The overall length of the bridge is 165.20 m. | |
ROAD BRIDGE OVER THE DANUBE IN NOVI SAD – SERBIA "VARADINSKI MOST" | HIGHWAY E – 75 STATE BORDER (HORGOS) - SUBOTICA - FEKETIC | |
A steel continuous beam across three plains spans the Danube using the piers of the destroyed steel trussed bridge.
The overall length of the bridge is 304,8 m. Fieldwork lasted 105 calendar days. | On the 71km State border - Feketic stretch of the International Highway E - 75, 30 (thirty) Bridges Overpasses, in total length of 2000 m, have been constructed. All Project were founded on piles, foundations and abutment supporting beams casted in situ, and piers, piers supporting beams and prestressed girders executed as precast elements. All spans of Overpasses are 26 m. | |
ROAD BRIDGE OVER THE RIVER SAVA IN BELGRADE, SERBIA "GAZELA" BRIDGE | ROAD BRIDGE OVER THE IMPOUNDED LAKE GAZIVODE | |
Spanning of the River Sava is performed by a steel framework structure consisting of three plains with a span of 41.60+249.92+40,48 m. The inclined and end piers have joint supports founded to caissons. By its conception the bridge is an original designing solution. Erection of the steel structure in great span is performed by the cantilever procedure on principle of cantilever erection. The overall length of the bridge with innundations iz 475.50 m. | The bridge is built at the locatin of the previous bridge over the River Ibar sunk by making a new lake. Erection of the arch structure, suspenders and the pavement structure is performed by two parallel cable-ways with a carrying capacity of 12 t each. The arch abutments and the piers on the shore are founded to fresh slate – phyllite. The overall length of the bridge is 323.65 m. | |
ROAD BRIDGE OVER MORACA – MONTENEGRO, (“Grlo”) | ROAD BRIDGE OVER THE DANUBE AT AT SMEDEREVO – SERBIA | |
The bridge of the continuous portal frame system with inclined intermediate piers and with a span of 14.0+64.0+17.0 m is built of reinforced and prestressed concrete. It is located at a height of 107 m above the river bed. The coastal parts of the bridge, the beams with inclined piers and nosings of 7.0 m, are concreted on the timber falsework strengthened by a steel structure and the steel rods. Intermediate – prefabricated part of the bridge is built of prestressed concrete with four girders 33,40 m long. The girders are erected by a crane-track support and two mobile portal cranes. All piers are founded to a limestone rock. It is the first bridge in this country built by prefabricated girders made of the prestressed concrete and longer than 30.0 m. The overall length of the bridge is 103.20 m. | The bridge consists of three steel continuous beams of a box cross-section with the upper orthotropic deck (plate) and the approach reinforced concrete prestressed structures. It is the longest bridge over the Danube across its ''water plane'' which is at normal water level 1,050 m and at high navigable level 1,200 m. All piers are founded to the bored piles, with 1.5 m diameter and built under the protection of cofferdams and sheet piling. Erection of the steel structure is performed by a floating crane. The overall length of the bridge is 1,436 m. | |
SCAFFOLD ROAD RAILWAY BRIDGE OVER THE DANUBE IN NOVI SAD –SERBIA | ROAD BRIDGE OVER THE RIVER VELIKA MORAVA AT MIJATOVAC – SERBIA | |
The river piers are founded to the bored piles of 1,50 m in diameter, braced by prefabricated reinforced concrete rings and pile helmets. Road and rail traffic flows by turns. The overall length of the bridge is 423,50 m. All work was completed in 100 calendar days. | The bridge is a prestressed structure across five plains of the continuous beam system. The intermediate piers are erected on the foundations of the destroyed bridge and the coastal piers are adjusted. The pavement structure consists of two main longitudinal girders with cross girders and bridge deck. They are made as the prefabricated elements, 5.22 m long, and then joined into prefabricated pieces with the maximal length of 20.40 m. They are erected by the launching truss. Such a thought-out technological procedure enabled fast and economical erecting of the bridge. The overall length of the bridge is 275.60 m. | |
ROAD AND HOT-WATER TRANSMISSION LINE BRIDGE OVER THE RIVER SAVA IN OBRENOVAC | ROAD BRIDGE OVER THE RIVER SAVA AT OSTRUŽNICA – SERBIA | |
The bridge consists of the steel braced structures of the simple beam system, with a span of 2x51.0+51.50+101.50+141.0+50.50 and a reinforced concrete structure with a span of 19.70+8x20.20m. These structures rest on 16 piers founded to HW piles with 1.20 and 1.50 m diameter. Two traffic lanes run along the middle of the bridge and one of the hot-water transmission lines and walkways are on each cantilever. The steel trusses are pre-erected on the river banks, and then carried to the piers by a floating crane. The overall length of the bridge is 446.50 m. | The biggest structure on Belgrade by-pass road consists of the approach the prestressed concrete structures on the left and right river banks and steel the continuous construction of a box cross-section with the upper orthotropic deck (plate). The bridge is built for the upstream half of the highway profile and the piers for the full profile. All piers are founded to bored piles with 1.5 m diameter. The approach concrete structures are the prefabricated reinforced concrete prestressed beams 593.35 m long on the left and 608.35 m long on the right bank. The erection is performed by a launching truss. The steel structure in the river flow is the continuous beam with five spans 3x99.0+88.0+198.0 m long. The erection is performed by a floating crane. The overall length of the bridge is 1,785.0 m. | |
ROAD BRIDGE OVER THE RIVER LIM IN PRIBOJ – SERBIA | FOOTBRIDGE OVER THE RIVER SAVA IN SREMSKA MITROVICA – SERBIA (ST. IRINEJ BRIDGE) | |
The bridge consists of two constructive ensembles: the reinforced concrete innundations on the right river bank with a span of 15.25+4x15.0+14.0 concreted on the falsework and the prestressed concrete structure in the river part of the span of 12.0+84.0+14.0 m The river piers are founded to a rock by means of a well and the others are founded in open pits. Great negative reactions at the end piers in the river parts of the bridge are transmitted to the mainland by permanent geoanchorages. The overall length of the bridge is 199.25 m. |
The concrete pylons are placed in the mid-plane of the bridge. The coastal and pylon piers are founded to piles, with 1.20 m diameter. The Erection of the steel structure and reinforced concrete bridge decks is performed by a floating crane. The overall length of the bridge is 297.50 m. | |
ROAD FLOATING BRIDGE OVER THE DANUBE IN NOVI SAD – SERBIA | ROAD - RAILWAY BRIDGE OVER THE DANUBE IN NOVI SAD – SERBIA | |
The bridge had been used until the Bridge of Sloboda is completed. It was removed on October 11, 2005. The bridge length with approach ramps was 369.60 m. All work was completed in 60 calendar days. | Two reinforced concrete arches with spans of 211 m and 165,75 m. By the type of construction they represented a unique solution in the world. For the large arch concreting, a falsework is constructed of prefabricated reinforced concrete elements by the cantilever procedure for the first time in the world. Till the ends meet in the crown of arch, cantilevers are supported by cables anchored in the arch abutments through temporary pylons. For the first time in Serbia a high percentage of the precast reinforced concrete prefabricated elements of a bridge permanently built-in the hanging roadway are applied to the bridge. These are: suspenders, cross girders, bracings and walkway elements. The arch abutments are built by the caisson method. The intermediate abutment area is 838 m2. The overall length of the bridge is 466,45 m. | |
ROAD BRIDGE OVER THE RIVER EUFRAT AT AL FALLUJAH – IRAQ | BRIDGES ON THE HIGHWAY – No1 IN IRAQ | |
The bridge structure consists of the river part with a span of 2x51.415+5x70.83 and two innundations of 2x18.0+2x6.1 m on the right river bank. The piers of the river part of the bridge are founded to the caissons with the area of 88.0 m2, and the innundation piers are founded to the bored piles of 1.5 m in diameter. The superstructure structure is made of the prestressed concrete except the innundation 2x6.1 m which is made of reinforced concrete. The overall length of the bridge is 505.18 m. |
The piers are founded to the bored piles with 1.2 and 1.5 m diameter. The road surface is made of prestressed concrete, mostly of a prefabricated type. The overall length of all bridges is 3,406 m. | |
ROAD BRIDGE OVER THE RIVER EUPHRATES, AL MUSAYYIB – IRAQ | ROAD BRIDGE OVER THE CHANNEL AL HILLAH IN IRAQ | |
The bridge is built of prestressed concrete. All piers are founded to bored piles with 1.20 m diameter. The superstructure structure consists of the prestressed prefabricated girders. The overall length of the bridge is 382.0 m. | The bridge is built of prestressed concrete across The piers are founded to piles with 1.5 m and 1.2 m in diameter. The superstructure structure consists of the prestressed prefabricated girders. The overall length of the bridge is 180 m. | |
ROAD BRIDGE OVER THE RIVER TIGRIS IN NAAMANIYAH – IRAQ | ||
The bridge is built of prestressed concrete and consists of a river construction with the spans of 13x36.0 m and The piers in the river part are founded to the bored piles with 1.5 m diameter and to innundations with 1.2 m diameter. The superstructure structure consists of the prestressed prefabricated girders. The overall length of the bridge is 594.0 m. |